Construction Progress Management System for PPC Implementation |
Authors |
Chul-woo Lim ; Jung-Ho Yu ; Chang-Duk Kim |
Keywords |
Last Planner System ; Lookahead Plan ; Weekly Work Plan ; PPC ; Time Management System |
Abstract |
Last Planner System (LPS) developed by Lean Construction Institute consists of four steps: Master Schedule, Phase Schedule, Lookahead Planning and Weekly Work Plan. This paper focuses on the process of measuring Percent of Plan Completed (PPC) at the Weekly Work Plan stage. PPC means the percentage of weekly assignments completed. According to the results of the researches that deal with PPC from many other countries, we can assure the benefits of using PPC. However, the concept of PPC is unfamiliar in Korea construction industry. This paper analyzes the cases in which PPC is applied in other countries and compares them with the production control system in Korean construction industry. The results of this research will provide the time management system for using PPC in Korea. |