Title |
Approximate Estimating of Plant Construction Duration Using a Standard Schedule Model |
Authors |
Moon, Sungwoo ; Park, Sangchun ; Kwon, Kinam |
Keywords |
standard schedule model ; preliminary estimating ; activity duration ; critical path ; activity relation |
Abstract |
The required level of detail in scheduling depends on the stages in the construction life-cycle. The objective of this study is to provide a Standardized Schedule Model (SSM) with an aim to facilitate the estimating of construction duration in the planning stage. The SSM modularizes work items; establishes relations between preceding and succeeding activities; and calculates approximate construction duration. The estimated duration of the SSM was compared with the detailed duration from the commercial scheduling tool using actual work activities. The difference showed to be ranged between -3.1% and +15%, which demonstrates that the SSM can be feasibly applied to the approximate estimation of construction duration. |