Extraction and Analysis of Construction Phase Risk Factors in High-rise Construction Project |
Authors |
Kim, Sooyong ; Kim, Sunghyun ; Yang, Jinkook |
DOI |
http://dx.doi.org/10.6106/KJCEM.2016.17.2.090 |
Keywords |
Preference Ranking Organization METHod for Enrichment Evaluation (PROMETHEE) ; Risk ; Focus Group Interview (FGI) ; High-Rise Construction |
Abstract |
High-rise buildings construction project have various risk factors. Major risk factors are negative results such as time delay and increase of costs. Therefore, this study was analyzed risk factors in construction stages of high-rise buildings using by PROMETHEE technique. For this, this research were identified risk factors through experts Focus Group Interview(FGI). And, PROMETHEE was used to setup evaluation standard for analysis of high-rise building construction risks. Next, the standard of evaluation index calculation was composed by using the definition level in PDRI. Preference function and evaluation index were identified through questionnaires. Through these processes, this study has calculated the importance of high-rise building construction risks using by PROMETHEE technique. As a result, high degree risk factors were as following. These are ‘Operation plan of material lifting ', ‘Outrigger & Belt Truss Construction',' Foundation work plan of high-rise building' and 'Considering a Structure concept of high-rise building'. |